Project managers from the Flagler Bridge construction site presented an update to the Town Council this week.

 

Flagler Bridge 1 April 2016They showed the detours necessary at Flagler Drive on the west end so the east bound ramp could be constructed and the old flyover demolition. 

They also showed aerial photos of the progress.  Later this year traffic will be moved onto four lanes instead of the current two. 

The project is scheduled for completion in 2017.