During Tuesday's Town Council Meeting this week, FDOT provided a status update on the Flagler Bridge Replacement Project. Their PowerPoint presentation is attached to this story.

  • Flagler Bridge Status PPT Opening SlideAll 12 pier foundations completed
    • Includes “abutments” at the east and west end of the bridge, 10 intermediate piers
  • Columns/Caps on 7 of 10 intermediate piers completed
    • Estimated completion in August
  • Main Bascule Piers 4 & 5 walls and slabs are poured
    • These will hold the mechanical components that raise and lower the bridge spans
  • Start setting concrete beams, fall 2015
    • Install main (moveable) bridge spans, late 2015
  • Eastbound traffic on new bridge, spring 2016
  • Project completion, early 2017